Major Orange County freeway closures planned: June 13-19

Here are major construction project closures happening on Orange County’s freeways and toll roads between June 13 and June 19, according to the Orange County Transportation Authority, Caltrans and the Transportation Corridor Agencies.

5 Freeway

Northbound carpool lane between Grand Avenue and State Route 57 and southbound carpool lane between Bristol Street/La Veta Avenue and First Street:

  • Scheduled to remain closed through the end of June

State Route 73

Southbound on-ramp from Greenfield Drive:

  • 5 a.m. to 1 p.m. Saturday, June 13

Northbound on-ramp from La Paz Road:

  • 5 a.m. to 1 p.m. Sunday, June 14

Ortega Highway

Westbound lane between post miles 5 and 4 near Gibby Road. This will be a flagging operation to allow vehicles through while the work is performed:

  • 6 a.m. to 1 p.m. Sunday, June 14

405 Freeway

Southbound on- and off-ramps from Goldenwest Street:

  • Scheduled to reopen Tuesday, June 23

Southbound on-ramp from Edinger Avenue:

  • Scheduled to reopen Wednesday, July 1

 Northbound loop off-ramp to Westminster Boulevard:

  • Closed in April for approximately one year

OC Streetcar

Detours, temporary lane closures and parking restrictions are expected daily on Fairview Street, West Santa Ana Boulevard, Main Street, by Sasscer Park, Fourth Street, Broadway, East Santa Ana Boulevard, French Street, Lacy Street and Santiago Street.

Construction schedules may change because of weather or other factors. Stay updated via TCAOCTA and Caltrans’ social media pages. 


Source: Orange County Register